SAP Solution Manager 7.2 – Task List XXX no Longer Conforms to the Current Definitions

During check task list or create incident in ChaRM in specific project You can see below error:

How You can resolve this error… SAP suggest:

  1. Close the current Project Cycle (this will close the Maintenance Cycle and Task List)
  2. Correct the Logical Component definition in Solution Manager
  3. Generate a new Project Cycle

Additional information can be found in point 6 from the following SCN blog Change Request Management: Usual Questions and Known errors

Before changing systems, logical components, or the TMS configuration, the project cycle must be closed. Changes to any of these once the task list is active are not supported.

If you want to see the assignments between the task list and the project, see the tables below:

/TMWFLOW/TTRCKHC
/TMWFLOW/VREPPRJ

Your email address will not be published. Required fields are marked *

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <s> <strike> <strong>

Copyright © 2024. SAPBasisWorld.com Privacy Policy